Garreg Fawr Energy Park

About Garreg Fawr Energy Park

We’re proposing an onshore renewable energy park called Garreg Fawr Energy Park. The park would be located approximately 9km north-west of Brecon and 15km south-west of Builth Wells in Powys.

The proposal includes 22 wind turbines generating approximately 154MW of clean, green energy, enough to power the equivalent of nearly 109,600 homes a year.*

We’re committed to ensuring Garreg Fawr Energy Park not only benefits the environment but also the local community. Based on our current designs, an annual Community Benefit Fund of up to £1.15 million would be available to support groups, places and projects every year, for the operational life of the park.

* – Average UK household consumption taken from RenewableUK

Meet the team

Garreg Fawr Energy Park site map

This draft turbine layout is indicative and will evolve with the design – and your input during the consultation periods will be really important in ensuring we get the design right, ready for application.

Our proposal includes:

  • 22 wind turbines, each with a maximum blade tip height of 220m.
  • Access track indicative layout. The delivery route for turbine components to site is still being explored, with further detail to be provided at the next stage of consultation.
  • Associated infrastructure including a substation, control building, wind measurement equipment and temporary construction and storage compounds. The locations of these have not yet been identified, but our submission for Environmental Impact Assessment Scoping Direction details the methodology for assessing the associated impacts.

Timeline

Project announcement:
Launch of our dedicated project website for
the energy park, including its indicative site
location and map of connection point to the grid.
Summer 2025
close xPrevious
Next
Project announcement:
Launch of our dedicated project website for
the energy park, including its indicative site
location and map of connection point to the grid.
Summer 2025

This marks the first time we share our initial plans for the energy park. At this stage, we can provide basic information, such as the likely number of turbines and the general location. Importantly, we want to involve local residents and communities from the outset, so we welcome early views and feedback that could help shape the plans as they develop.

Submitting a request to Planning and
Environment Decisions Wales (PEDW)
for direction on the scope of our
Environmental Impact Assessment (EIA)
August 2025
close xPrevious
Next
Submitting a request to Planning and
Environment Decisions Wales (PEDW)
for direction on the scope of our
Environmental Impact Assessment (EIA)
August 2025

This is an important early milestone in developing the project. The Environmental Impact Assessment (EIA) is a central document which sets out all of the surveys, assessments and reports we undertake to inform the design of the proposed energy park and ensure that we’re minimising potential environmental impacts. This process takes several months, and we must ensure that we assess all necessary environmental considerations. At this point we submit an overview of how we intend to undertake this work, and which surveys and assessments we’ll include. Through its ‘Scoping Direction’, (normally in the form of a letter), the department responsible for planning at Welsh Government (PEDW) will then tell us whether our proposed approach to delivering this is appropriate, and if we need to take any other issues into account.

Current PhaseProject transition to Infrastructure Consents Regime Summer 2026
Non-statutory engagement with
communities, specialist consultees
and other stakeholders
Ongoing throughout 2026
close xPrevious
Next
Non-statutory engagement with
communities, specialist consultees
and other stakeholders
Ongoing throughout 2026

This is our first round of consultations. During this stage, we continue carrying out environmental surveys and assessments to inform the draft Environmental Impact Assessment (EIA). At the same time, we begin shaping the design of the proposed energy park. To do this, we hold an ‘informal’ consultation round, where we present early proposals and invite feedback from communities, stakeholders and consultees. It’s known as ‘non-statutory’ consultation, because we aren’t required to undertake it, and we won’t yet have all the details about the plans – however we see great value in presenting our early plans in order to help inform the design process.

Statutory consultation with local
communities, specialist consultees
and other stakeholders
To be determined
close xPrevious
Next
Statutory consultation with local
communities, specialist consultees
and other stakeholders
To be determined

This is the formal consultation required before we submit our application. At this stage we’ll have a full ‘Draft’ Environmental Statement (ES), which sets out the conclusions of all the surveys and assessments we’ll have carried out, in line with PEDW’s Scoping Direction. We conduct a formal consultation for a period of at least 42 days. This consultation is a requirement before we can submit an application, which is why it is called ‘statutory consultation’. We’ll post formal notices in the paper and around the site, and notify relevant consultees, for example Natural Resources Wales and other environmental or technical consultees, local councillors and community councils, and those owning neighbouring land or living nearby. We’ll also host consultation events both in-person and online to present our proposed plans, before we submit them to PEDW for consideration.

Submission of an application for
a Development of National Significance
To be determined
close xPrevious
Next
Submission of an application for
a Development of National Significance
To be determined

At this stage we will submit our application. Once we have completed the statutory consultation, we’ll review all feedback and produce a Pre-Application Consultation (PAC) Report. The Report will set out the feedback received and explain how it has shaped the final plans. If we’re unable to act on certain points, we’ll provide clear reasons why. This report, alongside the full suite of application documents will then be submitted to PEDW for consideration – which will then make decision on whether or not to accept the application to commence the Examination process.