Project announcement: Launch of our dedicated project website for the energy park, including its indicative site location and map of connection point to the grid. Summer 2025
close xPrevious
Next
Project announcement: Launch of our dedicated project website for the energy park, including its indicative site location and map of connection point to the grid.Summer 2025
This marks the first time we shared our initial plans for both Lan Fawr and the earlier Bryn Rhudd Energy Park. At this stage, we could only provide basic information, such as the likely number of turbines and the general location. Importantly, we involved local residents and communities from the outset, so we welcomed early views and feedback that could help shape the plans as they developed.
Submitted a request to Planning and Environment Decisions Wales (PEDW) for direction on the scope of our Environmental Impact Assessment (EIA) Autumn/Winter 2025
close xPrevious
Next
Submitted a request to Planning and Environment Decisions Wales (PEDW) for direction on the scope of our Environmental Impact Assessment (EIA)Autumn/Winter 2025
This is an important early milestone in developing the energy park. The Environmental Impact Assessment (EIA) is a central document which sets out all of the surveys, assessments and reports we undertake to inform the design of the proposed energy park and ensure that we’re minimising potential environmental impacts. This process takes several months, and we must ensure that we assess all necessary environmental considerations. At this point we submitted an overview of how we intend to undertake this work for Lan Fawr and Bryn Rhudd Energy Parks, and which surveys and assessments we’ll include. Through its ‘Scoping Direction’, (normally in the form of a letter), the department responsible for planning at Welsh Government (PEDW) will then tell us whether our proposed approach to delivering this is appropriate, and if we need to take any other issues into account.
Non-statutory engagement with communities, specialist consultees and other stakeholders Late 2025
close xPrevious
Next
Non-statutory engagement with communities, specialist consultees and other stakeholdersLate 2025
This is our first round of consultations on Lan Fawr and Bryn Rhudd as separate parks. During this stage, we continued carrying out environmental surveys and assessments to inform the draft Environmental Impact Assessment (EIA). At the same time, we began shaping the design of the proposed energy parks. To do this, we held an ‘informal’ consultation round, where we presented early proposals and invited feedback from communities, stakeholders and consultees. It’s known as ‘non-statutory’ consultation, because we aren’t required to undertake it, and we won’t yet have all the details about the plans – however we see great value in presenting our early plans in order to help inform the design process.
Submission of merged site scoping report Mid 2026
close xPrevious
Next
Submission of merged site scoping reportMid 2026
The Environmental Impact Assessment (EIA) is a central document which sets out all of the surveys, assessments and reports we undertake to inform the design of the proposed energy park and ensure that we’re minimising potential environmental impacts.
We have submitted an overview of how we intend to undertake this work for Lan Fawr Fawr Energy Park as one single park since merging with Bryn Rhudd Energy Park. Through its ‘Scoping Direction’, (normally in the form of a letter), the department responsible for planning at Welsh Government (PEDW) will then tell us whether our proposed approach to delivering this is appropriate, and if we need to take any other issues into account.
Statutory consultation with local communities, specialist consultees and other stakeholders Summer 2027
close xPrevious
Next
Statutory consultation with local communities, specialist consultees and other stakeholdersSummer 2027
This is the formal consultation required before we submit our application. At this stage we’ll have a full ‘Draft’ Environmental Statement (ES), which sets out the conclusions of all the surveys and assessments we’ll have carried out, in line with PEDW’s Scoping Direction. We conduct a formal consultation for a period of at least 42 days. This consultation is a requirement before we can submit an application, which is why it is called ‘statutory consultation’. We’ll post formal notices in the paper and around the site, and notify relevant consultees, for example Natural Resources Wales and other environmental or technical consultees, local councillors and community councils, and those owning neighbouring land or living nearby. We’ll also host consultation events both in-person and online to present our proposed plans, before we submit them to PEDW for consideration.
Submission of an application for a Significant Infrastructure Project Late 2027
close xPrevious
Next
Submission of an application for a Significant Infrastructure ProjectLate 2027
At this stage we will submit our application. Once we have completed the statutory consultation, we’ll review all feedback and produce a Pre-Application Consultation (PAC) Report. The Report will set out the feedback received and explain how it has shaped the final plans. If we’re unable to act on certain points, we’ll provide clear reasons why. This report, alongside the full suite of application documents will then be submitted to PEDW for consideration – which will then make decision on whether or not to accept the application to commence the Examination process.